St. Louis Lambert International Airport West Chiller Plant – Chiller Replacement

WES was part of a design team to  replace an old out of date chiller in the West Chiller Plant of the airport. new chiller to   Our role was to provide the electrical design requirements.  

Services rendered:       Electrical

Project Features:

Design New Unit Substation Power Distribution System- 4160V to 480V

Converted Chiller and Pumps to 480V from 4160V

Design New VFDs to Control Pumps and Chiller

Busduct Distribution to Serve New Pump and Chiller

Back to projects